Knowledge Base:  
Bradley WS-2WMD Dual Station Wall saver Shower (Multi Stall ) Stainless Steel,Bradley WS-3WMT Three Station Wall Saver Shower installation instructi
Last Updated: 03/24/2008
Installation Instructions

Step 1: Install shower
NOTE: Flush supply lines before making connections.
1. Rough-in supply piping to your shower as shown in Figure 1.
NOTE: Use the cold inlet location for tempered supply.
2. At dimensions shown in Figure 1, mark two wall bracket
anchor locations using wall bracket as a template.
3. Install wall anchors for 1/4" diameter screws at marked locations
(anchors and screws supplied by installer).
4. Secure two wall brackets to wall anchors with 1/4" diameter
screws (supplied by installer)
(see Figure 1).
5. Hang back of shower onto two wall brackets installed in Step 1.
6. Secure bracket on bottom cover of shower to wall with 1/4"
anchors and screws (supplied by installer).
7. Remove eight #10-24 x 1/2" button head screws which secure
the top cover to the showershell and lift top cover off.
8. Connect water supply to copper tubes inside shower body.
NOTE: Supplies can be brought in from back of shower or through knockouts located on top shower.
9. Turn on water to your shower and check for leaks.
10. Refasten top cover to showershell with eight #10-24 x 1/2" button head screws.

Vertical Shroud Installation (Optional)
1. Position wall bracket on top of shower as shown in Figure 2 and secure with 1/4" diameter
screws (supplied by installer).
2. Position slip ring against ceiling and in line with bracket installed in Step 1 (see Figure 2).
3. With bracket and slip ring secured, position shroud in place and secure shroud to lower bracket
with screws provided (see Figure 2).
4. Using holes at top of shroud as a template, drill and tap #10-24 holes in slip ring.
5. Secure shroud to slip ring with #10-24 screws provided (see Figure 2).

Horizontal Shroud Installation (Optional)
1. Position bracket and slip ring in place on wall where desired and
secure to wall with 1/4" diameter screws (supplied by installer) (see Figure 3).
2. Position shroud in place over the bracket and secure shroud to bracket with #10-24 x 1/2"
screws provided (see Figure 3). 3. Using shroud as a template, drill and tap #10-24 holes (use 5/32
drill) in slip ring. Secure shroud to slip ring with #10-24 x 1/2" screws provided (see Figure 3).

NOTE: Shroud mounting holes may be punched in front face of shroud.

Attachments:   03/24/2008: ws-3WMT inst.pdf


Was this article helpful?

Comments:
 

Related Articles
 > Installation Instruction for Bradmar Partitions
 > INSTALLATION INSTRUCTIONS FOR BOBRICK LAMINATED PLASTIC TOILET PARTITIONS 1030 TrimLine™ Series • 1040 Designer™ Series • 1840 FRP™ Series
 > INSTALLATION INSTRUCTIONS solid phenolic TOILET partitions 1080 DuraLineSeries™ • 1180 DuraLineSeries™ Class-A Fire Rated
 > INSTALLATION INSTRUCTIONS 1090 SIERRA™ SERIES TOILET PARTITIONS WITH HEAVY-DUTY HARDWARE
 > INSTALLATION INSTRUCTIONS LAMINATED PLASTIC TOILET partitions 1540 ClassicSeries™ with Options
 > Bradley Lenox Locker Installation Instructions
 > Bradley Lenox Pedestal Bench Installation
 > Bradley Lenox Locker Bench Installation
 > Bradley Panelon Shower system installation Instructions
 > Bradley Column shower Installation Instructions
 > Bradley Column beach Shower COL-5C-HN, COL-4C-HN, COL-3C-HN, COL-2C-HN Installation
 > Bradley Column beach Shower COL-5C-HN, COL-4C-HN, COL-3C-HN, COL-2C-HN
 > Bradley Adapt-A-Brad Conversion instructions
 > Installation Instructions for Bradley 1W (Bradsole), 2W, 3W, 1K & 1F Econo-Wall™ Showers